What are my rights when a builder will not pay me in Queensland?

In Queensland the Building Industry Fairness (Security of Payment) Act 2017 lets a subcontractor serve a payment claim, forces the builder to answer within 15 business days, and makes the full amount payable if they do not. If you are still unpaid you can apply to the QBCC Adjudication Registry for a fast decision, sue for the debt, or stop work after giving 2 business days written notice.

The Academy is at full capacity. 9,000+ owners trained, 4.9 stars from 123 Google reviews.

What law protects subcontractors in Queensland?

The Building Industry Fairness (Security of Payment) Act 2017, known as the BIF Act, protects anyone who carries out construction work or supplies related goods and services in Queensland. It sets strict deadlines for payment, gives you a fast adjudication process run through the QBCC, and lets you stop work safely when you are not paid. It replaced the old BCIPA and the Subcontractors Charges Act in December 2018.

The Act has three working parts that matter to a subcontractor:

  • Chapter 3: progress payments, payment claims, payment schedules, adjudication and the right to suspend.
  • Chapter 4: subcontractors charges, which let you claim against money the owner still owes the builder.
  • Chapter 2: statutory trusts, which protect money on larger projects.

Am I covered if I work for a builder on a house?

Yes. The Act applies to written and verbal agreements alike (s 61 and s 64), so a quote accepted by text is enough. The only residential exclusion is for a contract where a resident owner is a party (s 61(2)(b)). Your contract is with the builder, not the homeowner, so you keep every right in the Act even on a house build.

Two more points:

  • You cannot sign your rights away. Section 200 prohibits contracting out of the Act.
  • You must hold the right licence. Under s 42 of the Queensland Building and Construction Commission Act 1991, a person who does building work without the required licence is not entitled to be paid for it beyond limited costs, and cannot use the BIF Act to recover it. Check your licence class covers the work before you start.

How do I make a valid payment claim in Queensland?

A payment claim under s 68 must identify the work, state the amount claimed and request payment. A document headed "invoice" satisfies the request element, and since 2018 you no longer need to state that it is made under the Act. You can make one claim for each reference date, which is the date in your contract or, if there is none, the last day of each month in which you worked.

Time limits under s 75:

  • Progress claims: within the period in your contract or 6 months after you last did work, whichever is later.
  • Final claims: within the latest of the contract period, 6 months after completion of all work, or 28 days after the last defects liability period ends.

Serve it in a way you can prove. Email to the address in the contract, with the invoice attached and the work itemised, is the practical standard.

What must the builder do, and by when?

If the builder disputes any part of your claim, they must give you a payment schedule within the earlier of the contract time or 15 business days (s 76). The schedule must state what they will pay and give every reason for paying less. If they give no schedule, they become liable for the full claimed amount on the due date (s 77), and they lose the right to answer an adjudication (s 82(2)).

When payment falls due:

  • If your contract is silent: 10 business days after the claim (s 73).
  • The legal maximum for a subcontract: 25 business days, under s 67U of the QBCC Act. A longer term in your contract is void.
  • Pay when paid clauses have no effect (s 74). The builder cannot hold your money because the client has not paid them.

Failing to pay an amount the builder has scheduled is an offence, and the QBCC can take disciplinary action against a licensee who ignores a claim.

What can I do if the builder still does not pay?

You have two main routes. The fastest is adjudication through the QBCC Adjudication Registry (s 79): an independent adjudicator decides the amount, usually within weeks, and the decision can be filed in court as a judgment. The alternative is to sue for the unpaid amount as a debt (s 78), where the builder cannot raise defences arising under the contract (s 100).

Deadlines to apply for adjudication:

  1. Schedule given for less than you claimed: within 30 business days after you receive it.
  2. Schedule given but the amount not paid: within 20 business days after the due date.
  3. No schedule and no payment: within 30 business days after the later of the due date and the last day a schedule could have been given.

What happens next:

  • Give the builder a copy of the application within 4 business days.
  • The builder can only rely on the reasons in their schedule (s 82(4)).
  • The adjudicator usually decides within 10 business days of the response (s 85), longer for complex claims over $750,000.
  • The builder must pay within 5 business days of the decision (s 90), or you file the adjudication certificate in court as a judgment debt (s 91 and s 93).

To sue instead, give the builder a warning notice within 30 business days after the due date and wait at least 5 business days before starting proceedings (s 99).

One more tool most subcontractors miss: once you have applied for adjudication, a payment withholding request (s 97B) can require the party above the builder to hold back money owed to the builder until your claim is resolved. It cannot be given to a resident owner.

Can I stop work until I am paid?

Yes, under s 98. If the builder does not pay in full by the due date, or does not pay an adjudicated amount, you can give written notice that you intend to suspend work under the BIF Act. You can stop at least 2 business days after the notice is given and stay off the job until you are paid. A lawful suspension is protected, so you are not in breach of contract for stopping.

Do not walk off without the notice. Stopping without it can be treated as abandoning the contract, which hands the builder a claim against you.

What extra protections apply in Queensland?

Queensland gives subcontractors two protections most states do not: subcontractors charges and statutory trusts. A charge lets you claim against money the owner still owes the builder. Trusts ring fence project money on larger jobs. Both have strict thresholds and deadlines, so check them early.

Subcontractors charges (Chapter 4)

  • Give a notice of claim of charge to the owner or higher contractor, certified by a qualified person (s 122).
  • Do it during the work or within 3 months after practical completion (for retention only, within 3 months after the defects liability period ends).
  • Start court proceedings within 1 month after giving the notice (s 136), or the charge ends.
  • You cannot run a charge and an adjudication for the same payment dispute. Get legal advice before choosing.

Project and retention trusts (Chapter 2)

  • Required on eligible contracts of $1 million or more for Queensland Government and Hospital and Health Service work, and $10 million or more for private and local government work.
  • Further phases planned for 2025 were paused, and no new dates have been set.
  • Cash retentions on those jobs must sit in a retention trust account.

Business days

Business days exclude weekends, public holidays and every day from 22 December to 10 January. A claim served just before Christmas gives the builder well over a month.

What should I do today if I have not been paid?

Work the steps in order and keep a dated record of every document. The deadlines run against you as well as the builder, and most lost claims are lost on a missed date or a claim that cannot be proved.

  1. Check your licence covers the work.
  2. Serve a clear payment claim by email: the work, the amount, a request for payment.
  3. Diary the schedule deadline (15 business days) and the due date.
  4. If the due date passes unpaid, serve a written notice of intention to suspend under s 98.
  5. Apply to the QBCC Adjudication Registry inside the deadline that applies to you, and consider a payment withholding request.
  6. For large or disputed amounts, get a construction lawyer to check the paperwork before you lodge.

The businesses that rarely end up here run this as a system rather than a fight: every progress claim goes out in a form that keeps their rights live, and an AI agent tracks each claim's dates so the notice goes out the day a deadline is missed rather than a month later.

Where is this in the legislation?

This is general information about the law as at 16 October 2026, not legal advice. Deadlines depend on your contract and the facts, so get advice from a Queensland construction lawyer before relying on it for a large or disputed claim.

Also asked

More questions owners ask.

Does my invoice need to say it is made under the BIF Act?

No. Since the BIF Act started in December 2018 a payment claim only needs to identify the work, state the amount and request payment. A document headed invoice meets the request requirement. Many subcontractors still add a line saying it is a payment claim under the Act, which does no harm and removes any argument.

Can a builder take my work off me because I suspended?

A suspension done properly under s 98, after 2 business days written notice, is protected. You are not in breach for stopping, and if the builder removes your work from the contract because you suspended, you can pursue the loss that causes you. The protection only exists if the notice was given first.

How much does QBCC adjudication cost?

You pay a lodgement fee to the QBCC Adjudication Registry and the adjudicator's fees, which the adjudicator usually splits between the parties and can order the builder to pay. Check the current fee on the QBCC adjudication page before you lodge. For most unpaid claims it costs far less than court.

What if the builder goes broke before paying me?

Move early. A subcontractors charge can attach to money the owner still owes the builder, and a payment withholding request can freeze money above the builder once you have applied for adjudication. Both depend on strict deadlines, and neither helps once the money has been paid out, so act as soon as payment stops.

Why Greg

You speak to the owner who has already done it.

Greg built Response Electricians in Perth into a 30+ staff business with 1,950+ five-star reviews. A general manager runs it.

He has trained 9,000+ trade business owners across Australia and New Zealand.

He grew a coaching company to 35 staff, a CEO and 15 coaches, then cut it back so every owner deals with him directly.

Most coaching companies hand you to a salesperson, then to a coach who has never run a trade business. Here you get the owner.

The Academy is full because it works, and Greg keeps it small on purpose so every business gets looked at properly, by him. He reads every application himself, interviews the owners who fit and only takes on owners who are building for the right reasons and give back to the group. Join the waitlist and he'll be in touch when a place opens.

Illustration: a trade business owner standing over three office staff buried in paperwork at night.
The old way

More customers meant more people doing the computer work, and more wages nobody invoices.

Illustration: a tradesman shaking hands with a homeowner in her driveway, his phone showing jobs quoted and invoiced.
The new way

You stay with your customers and your team. The office stops landing on you.

The old way

More jobs. More paperwork. Less of the owner left.

Most trade businesses grow the same way.

More jobs means more quoting, invoicing, chasing and scheduling.

None of it gets paid for.

So the owner does it at night, after a full day on site.

Or hires an office person to do it.

The office grows. The wages grow. The margin does not.

And the owner is still the one everything waits on.

Where we take you

More work. More profit. More of you left.

The phone rings with the jobs you want, at the price you set.

You grow when you're ready, never faster than the business can carry.

Every job is priced to make money, so the busy months show up in the bank.

The best tradies in your area want to work for you, and they stay.

The chasing, the paperwork and the 9pm admin stop landing on you.

The business runs the day. You pick which parts of it you're in.

Bigger, without the headaches. Getting bigger stops meaning getting busier.

P.S.

P.S. Joining the waitlist costs nothing and there is no obligation. While you wait, the Tradies App is free with an active ABN, so you can start on the lessons tonight.