What are my rights when a builder will not pay me in the ACT?

In the Australian Capital Territory the Building and Construction Industry (Security of Payment) Act 2009 lets a subcontractor serve a monthly payment claim stating it is made under the Act. The builder must answer within 10 business days or owes the full amount, and since March 2024 must pay within 15 business days at most. If unpaid, you can adjudicate, sue for the debt, or stop work after 2 business days written notice.

The Academy is at full capacity. 9,000+ owners trained, 4.9 stars from 123 Google reviews.

What law protects subcontractors in the ACT?

The Building and Construction Industry (Security of Payment) Act 2009 gives anyone who carries out construction work or supplies related goods and services in the ACT a statutory right to progress payments. It sets deadlines for the builder to respond and pay, gives you adjudication, and lets you stop work safely when you are not paid. ACT Planning publishes the official guidance.

The Building and Construction Legislation Amendment Act 2023 made the most recent substantive changes, in force from 11 March 2024:

  • Monthly claims replaced reference dates.
  • Claims on termination are allowed from the day the contract ends.
  • Payment is capped at 15 business days after the claim, even where the contract names a later date.

Am I covered if I work for a builder on a house?

Yes. The Act does not apply to residential building work where a resident owner is a party to the contract, unless the work is under an owner builder licence. That exclusion only catches the contract the homeowner signs, not your subcontract with the builder. ACT guidance confirms the Act covers you even if the contract is not written, and s 42 makes any contract term that tries to exclude it void.

How do I make a valid payment claim in the ACT?

A payment claim under s 15 must identify the work, state the amount claimed, and state that it is made under the Act. Use this wording: "This is a payment claim made under the Building and Construction Industry (Security of Payment) Act 2009 (ACT)." Since 11 March 2024 you can claim on or after the last day of each month in which you did work, or an earlier day the contract sets.

When and how often you can claim:

  • Monthly (s 10), from the last day of the month in which you first did work.
  • On termination, from the day the contract is terminated.
  • Time limit (s 15(5)): within the period in the contract or 12 months after you last did work, whichever is later.
  • Serve it in a way you can prove, by email to the address in the contract.

What must the builder do, and by when?

If the builder will pay less than you claimed, they must give you a payment schedule within the time in the contract or 10 business days, whichever is earlier (s 16). The schedule must identify your claim, state the amount they will pay, and give every reason for paying less. If no schedule arrives in time, the builder is liable for the full claimed amount (s 16 and s 17).

When payment falls due:

  • The cap (s 13): the earlier of 15 business days after the claim or the date the contract sets. A contract cannot push payment later.
  • Pay when paid and pay if paid clauses have no effect (s 14).

What can I do if the builder still does not pay?

You choose between adjudication and court. Adjudication runs through an authorised nominating authority: an adjudicator decides within 10 business days of the response, and the decision is filed in court as a judgment debt. Or you sue for the unpaid amount as a debt (s 17), where the builder cannot bring a cross claim or raise a defence arising under the contract.

Adjudication deadlines under s 19:

  1. Schedule for less than you claimed: apply within 10 business days after you receive it.
  2. Schedule given but the amount not paid: apply within 20 business days after the due date.
  3. No schedule at all: notify the builder of your intention to apply within 20 business days after the due date, giving them 5 business days to provide a schedule. Then apply within 10 business days after those 5 days end.

How it runs from there:

  • The builder can respond only if they gave a schedule in time, within the later of 7 business days after receiving the application and 5 business days after the adjudicator accepts (s 22).
  • They cannot add reasons that were not in the schedule (s 22(4)).
  • The adjudicator decides as soon as possible, and no later than 10 business days after the response is received or due.
  • If the builder still does not pay, obtain an adjudication certificate (s 26) and file it in court as a judgment debt (s 27). To challenge that judgment, the builder must first pay the amount into court.

Can I stop work until I am paid?

Yes, under s 29. If the amount owed is not paid, give the builder written notice that you intend to suspend work under the Act. You can stop 2 business days after the notice and stay off the job until 3 business days after you are paid. ACT guidance confirms you are not liable for the builder's loss caused by a lawful suspension.

Never simply stop turning up. Stopping without the notice can be treated as abandoning the contract.

What extra protections apply in the ACT?

The ACT has no statutory retention trust, project trust account or head contractor supporting statement, so the payment process and its 15 business day cap are the main protections. Your contract governs retention, so negotiate its amount and release date in writing before you start.

Business days exclude weekends and public holidays. If a deadline runs over Christmas, check the Act's current definition before you rely on it.

What should I do today if I have not been paid?

Work the steps in order and keep a dated record of each one. The ACT's 15 business day cap is one of the shortest in the country, which means a builder who is late is late quickly and you can move quickly too.

  1. Serve a payment claim by email with the work itemised, the amount, and the statement that it is made under the Act.
  2. Diary the schedule deadline (10 business days) and the due date (no later than 15 business days).
  3. If the due date passes unpaid, serve written notice of intention to suspend under s 29.
  4. Apply for adjudication inside the window that applies to you, or sue for the debt.
  5. For large or disputed amounts, have an ACT construction lawyer check the paperwork before you lodge.

The businesses that rarely end up here run it as a system rather than a fight: every monthly claim carries the statutory wording, and an AI agent tracks each claim's dates so the notice goes out the day a deadline is missed.

Where is this in the legislation?

This is general information about the law as at 16 October 2026, not legal advice. Deadlines depend on your contract and the facts, so get advice from an ACT construction lawyer before relying on it for a large or disputed claim.

Also asked

More questions owners ask.

What changed in the ACT in March 2024?

The Building and Construction Legislation Amendment Act 2023 replaced reference dates with a monthly right to claim, allowed claims on termination, and capped payment at 15 business days after the claim even where the contract names a later date. Before that the statutory period applied only where the contract was silent.

Is a homeowner contract covered in the ACT?

Not where a resident owner is a party, except work done under an owner builder licence. That exclusion only applies to the contract the homeowner signs. A subcontractor working for the builder on the same house has a separate contract and is covered.

Do I need a written contract in the ACT?

No. ACT Government guidance confirms you can claim under the Act even if the contract is not written. Keep the quote, the acceptance, your timesheets and photos of the work, because you still have to show what was agreed and what you did.

Why Greg

You speak to the owner who has already done it.

Greg built Response Electricians in Perth into a 30+ staff business with 1,950+ five-star reviews. A general manager runs it.

He has trained 9,000+ trade business owners across Australia and New Zealand.

He grew a coaching company to 35 staff, a CEO and 15 coaches, then cut it back so every owner deals with him directly.

Most coaching companies hand you to a salesperson, then to a coach who has never run a trade business. Here you get the owner.

The Academy is full because it works, and Greg keeps it small on purpose so every business gets looked at properly, by him. He reads every application himself, interviews the owners who fit and only takes on owners who are building for the right reasons and give back to the group. Join the waitlist and he'll be in touch when a place opens.

Illustration: a trade business owner standing over three office staff buried in paperwork at night.
The old way

More customers meant more people doing the computer work, and more wages nobody invoices.

Illustration: a tradesman shaking hands with a homeowner in her driveway, his phone showing jobs quoted and invoiced.
The new way

You stay with your customers and your team. The office stops landing on you.

The old way

More jobs. More paperwork. Less of the owner left.

Most trade businesses grow the same way.

More jobs means more quoting, invoicing, chasing and scheduling.

None of it gets paid for.

So the owner does it at night, after a full day on site.

Or hires an office person to do it.

The office grows. The wages grow. The margin does not.

And the owner is still the one everything waits on.

Where we take you

More work. More profit. More of you left.

The phone rings with the jobs you want, at the price you set.

You grow when you're ready, never faster than the business can carry.

Every job is priced to make money, so the busy months show up in the bank.

The best tradies in your area want to work for you, and they stay.

The chasing, the paperwork and the 9pm admin stop landing on you.

The business runs the day. You pick which parts of it you're in.

Bigger, without the headaches. Getting bigger stops meaning getting busier.

P.S.

P.S. Joining the waitlist costs nothing and there is no obligation. While you wait, the Tradies App is free with an active ABN, so you can start on the lessons tonight.