By Greg Allan, tradesman and creator of Data First Coaching
Why does a weather day cost more than the day itself?
A rained-off day on a brickwork job often costs more than the wages paid that day, because the price was built on a set number of working days and every day lost to weather shrinks that number without shrinking what the crew is paid. The labourer still turns up, mixes nothing, loads out nothing, and the bricks that were meant to cover the cost stay in the pack.
The scaffold does not come down because it is raining. Hire keeps ticking over whether a brickie lays a single face brick or not. The builder's progress payment is tied to brick count on the wall, not to days spent standing on site waiting for a break in the weather. So the job still owes the same money out, and the job still earns the same money in, only later, with fewer days to earn it in.
Why does the invoice total look the same while the margin gets thinner?
Most bricklayers do not see a weather day as a loss because the final invoice still matches the quote. The builder pays for the brickwork that went up, whether it took three weeks or five. What does not show on that invoice is how many paid days it actually took to lay it.
A job priced per thousand bricks or on a day rate has a number of billable days baked into it. When some of those days go to rain, cleaning down a wet site, or standing down a labourer who still gets paid, the same overhead and the same crew cost gets spread over less actual brickwork. The gross profit margin on that job quietly thins out, and because the invoice looks fine, nobody notices until the month is totted up and the BAS shows less cash sitting there than expected.
What number actually tells a bricklayer what a weather day cost the job?
The number that matters is billable hours against hours paid, tracked for every person on the crew, not just the bottom line of the finished job. That is the figure that shows whether a day rate quote is still standing up once weather, scaffold hire and a labourer mixing nothing are all counted in.
Most bricklayers only ever check this at tax time, if at all, because pulling it together by hand across footings, blockwork, retaining walls and feature brick jobs run through a season is slow work nobody has time for. By then the season that ate the margin is finished and the next one is already underway. Checking gross profit margin at the point of quoting, not after the job wraps, is what lets you see a weather-heavy job for what it actually costs before you are locked into the price.
How do you work out how many billable days a job really has before you price it?
You price the job around the real number of billable days it is likely to get, not the calendar days it sits on the schedule, and you build weather into that number before you quote it rather than discovering the shortfall once the job is underway. Picture a brickie quoting a retaining wall and feature brick job through a wet stretch of the season, with a labourer on day rate and scaffold already on hire.
If the quote assumes every scheduled day is a laying day, the job is already behind before the first brick goes up. When you price against the billable days you can genuinely expect, including the ones you will lose, you can present the builder with options, a straight day rate, a faster crew size, or a staged schedule, and close on a date that is actually booked in, not a number sitting in an inbox waiting on the weather to decide for you.
Could AI agents help you track this without more paperwork?
Yes, and this is where most bricklayers get stuck, because tracking billable hours against hours paid for a full crew across a season is exactly the kind of office work that eats an evening and still gets skipped. An AI agent is software that does a job the way you would do it yourself, using your prices, your wording and your rules, so it can sit in the background and do this tracking for you.
AI agents can watch billable hours against hours paid for each labourer and each job as the data comes in, flag when a run of weather days has started eating into a job's margin, and surface it while there is still time to adjust the crew or talk to the builder, rather than after the job is invoiced and closed. That is the shift data first coaching is built around: the problem gets caught at the point it starts, not months later in a bookkeeping review.
How does Data First Coaching approach this?
Data First Coaching starts from your own numbers through the Trade Business Intelligence, not from a guess about how many weather days a season usually costs. For a bricklaying business that means looking at billable hours against hours paid across the crew, job by job, to find where a quote stopped matching reality, rather than treating a thin month as a one-off. Greg Allan built this from running his own trade business, and he puts it plainly: “how many billable days are you going to be working?” is the question most owners never ask before they price the job. The how, the systems and the build, are worked through inside the Academy, with members, because the Trade Business Intelligence is powered by every member who is open minded, innovative and willing to share.